Construction of Sewage Network in the Municipality of Gradačac

The aim of the project is construction of a new sewage network in the northern part of the municipality of Gradačac.

The project foresees construction of a new sewage network will be built in the urban area and settlements in the northern part of the municipality of Gradačac. Within the project will be covered the following settlements and areas: Škorići, Sibovac, Bagdale, settlement Osoji (between Škorići and Sibovac), Vida 1, Vida 1 – school, Vida 2, Hazna and Hospital.

During the 2017-2018 period tendering procedure was completed in Czech Republic and supplier of equipment has been chosen. By the end of 2018 all equipment was delivered from Czech Republic to Gradacac. The works started in September 2018 and are almost completed in Skorići (cca. 3 km). The construction works in Bagdale, Hazna, part of the city centre and hospital have been contracted and should start in the first quarter of 2019. The signing of contracts for the rest of the works is expected in 2019.

Website:
www.gradacac.ba

Contact: 
Aziz Hodžić, Advisor for international Projects, Gradačac, aziz.hodzic@gradacac.ba

Project duration:
2017 - 2019
Themes:
Environmental governance, Local infrastructure
Status:
Completed
Strategic partner:
Local Governments, Municipality of Gradačac
Implementer:
Czech Development Agency (CDA), Municipality of Gradačac
Donor:
Government of Czech Republic
Project implemented in:
Federation of Bosnia and Herzegovina
Cantons:
Tuzla Canton
Municipalities (1):
Gradačac